# What Does It Cost to Build a Padel Court in the UK?

A useful starting point is the LTA’s **2025 benchmark of £71,000 for one outdoor padel court, excluding VAT and fees**. It separates £36,000 for the court with lights from £35,000 for the ring beam, base, ducting and drainage. It is a historical planning reference—not a guaranteed 2026 quotation, a national average or an all-inclusive budget for your site.[^S01]

To find out what your court will cost, you need a site-specific offer covering both the playing enclosure and the work required to install it. A cheaper advertised court package can be a much smaller purchase, not a cheaper version of the same finished project.

This guide concerns **one uncovered outdoor court in the UK, priced in GBP**. Indoor buildings, canopies, land acquisition and operating a club are separate budget questions.

## A useful benchmark, with its limits attached

The LTA’s construction guidance gives a more informative starting point than a single unexplained headline price because it identifies two substantial cost groups.

| Component | LTA single-court benchmark | Price basis | VAT and fees |
|---|---:|---|---|
| Court with lights | £36,000 | UK projects delivered in 2025 | Excluded |
| Ring beam, court base, ducting and drainage | £35,000 | Same benchmark | Excluded |
| Combined total | **£71,000** | Sum of the two groups above | **Excluded** |

The guidance says the figures include **some** site-specific costs, with actual costs depending on the location and site conditions. “Some” is not “everything your project needs.” Do not add the £35,000 again to an offer that already includes equivalent groundworks, or assume that a £36,000 structure-and-lighting figure covers the whole installation.[^S01]

Why not offer a broad current market range? Public contractor pages are not consistently comparable. Lofthouse’s article dated 19 January 2026 discusses different commercial packages but does not state a VAT basis. S&C Slatter’s public cost discussion does not establish a dated, VAT-explicit quotation suitable for a like-for-like comparison. Their headline numbers therefore cannot be combined into a defensible all-in 2026 range.[^S03][^S04]

The practical answer is to keep the LTA figure attached to its year and exclusions, then replace each relevant allowance with an actual quotation for your site.

## What an installed outdoor court quote must include

Ask the contractor to divide its offer into identifiable work packages. “Court supplied and installed” is still ambiguous unless it says what the installer expects to find on arrival.

Use the following as a request-for-quotation schedule. It is a checklist of questions, not a claim that every item is included in the LTA benchmark or in every contractor’s package.

| Work package | What the offer should make explicit |
|---|---|
| Court system | Named structure, glass, mesh, surface, net and access configuration; exact technical specification. |
| Site preparation | What demolition, excavation, removal and disposal are included; who handles unexpected conditions. |
| Foundations and base | Design responsibility, the proposed system and the condition of any base being reused. |
| Drainage | Court drainage, the discharge arrangement and who establishes that it is suitable for the site. |
| Lighting and electrical work | Light fittings and supports versus cables, controls, connection and commissioning. |
| Delivery and installation | Transport, unloading, lifting equipment, assembly, installer travel and access assumptions. |
| Handover | Inspections, operating instructions, maintenance information and the stated warranty responsibilities. |

The important distinction is between an item being **present** and the contractor being responsible for making it **work as part of the project**. Lighting fittings on a material list do not answer who connects them to the supply. A drainage line does not explain where the water is intended to go.

Give every bidder the same drawing and intended use. Our [court-dimensions guide](https://padel.how/rules/court-dimensions/) helps you describe the playing specification, while [court basics](https://padel.how/how-to-play/padel-court-basics/) explains the main parts of the enclosure. Neither replaces the designer’s assessment of the whole site.

Avoid specifying only a desirable label such as “panoramic.” Ask which exact system is being offered and what documents support its suitability for the proposed location. Price comparisons become useful only after the underlying specification is clear.

## Costs outside the playing enclosure

Make a second schedule for costs that can sit outside a court supplier’s offer. Ask about surveys, professional design, application work, access routes, surrounding works, utility connections and any facilities beyond the court. Mark each one “included”, “separately quoted” or “not yet assessed”; do not leave blanks that look like zeroes.

Planning is particularly easy to mistake for a minor administrative extra. The technical rules of a sport do not grant local permission. FIP documentation describes the playing environment; the local planning authority considers a development in its own context.[^S02][^S06] Our [FIP rules guide](https://padel.how/rules/official-fip-padel-rules/) is a technical reference, not a planning approval.

A concrete English example shows why the distinction matters. On **7 September 2026**, Wychavon District Council refused application **W/26/01384/FUL** for two padel courts with lighting. Its reasons included the absence of a noise and vibration impact assessment needed to consider the effect on nearby residents.[^S05]

That does not mean every UK court requires the same report or will receive the same decision. It means your budget should identify what your authority needs before you assume the construction package is the whole project. Ask about noise, lighting, operating hours and the evidence required for this location. The cited national planning guidance applies to England; check the relevant national and local process elsewhere in the UK.[^S06]

Keep VAT visible from the beginning. Request the net price, VAT treatment and amount payable rather than assuming an advertised figure is inclusive. Whether your organisation can recover any VAT is a separate, project-specific question for your adviser—not a discount to presume when comparing tenders.[^S07]

## Why a canopy or indoor court needs a different estimate

Treat a cover as a separate design and pricing exercise, not as a percentage to add to an outdoor-court headline.

Ask a canopy supplier to define its structure, foundations, drainage, erection, connections with the court and the weather protection actually provided. Ask the court supplier which parts of its original design would change. Without that coordination, two apparently complete offers may leave responsibility for the connection between them unresolved.

For a court inside an existing building, investigate the building as well as the court package. Ask the relevant professionals about clear space, the existing floor, access, lighting, ventilation and the permissions or adaptations associated with the proposed use. These are questions to resolve, not a claim that the same alterations are necessary in every building.

A new indoor hall is a different project again. Do not compare its total with an outdoor structure-only price and label the difference “the cost of a roof.”

Our [indoor-versus-outdoor guide](https://padel.how/equipment/indoor-vs-outdoor/) explains the playing and equipment context. For a construction decision, insist on a separate scope and quotation for each scenario. No canopy or indoor price is included in the £71,000 benchmark above.

## How to request and compare like-for-like quotes

Send the same brief to each contractor: location, one uncovered court, intended use, drawings, known site conditions, access constraints and the target specification. Ask for a dated offer in GBP with a validity period.

A useful comparison sheet puts the scope before the total:

| Field | What to record for each offer |
|---|---|
| Price date and validity | When the amount was issued and when it expires. |
| Net amount, VAT, amount payable | Keep all three visible; identify any item with different treatment. |
| Inclusions and exclusions | Use the same work-package rows for every bidder. |
| Fixed sums and allowances | Identify which amounts can change and what triggers a variation. |
| Client responsibilities | Work, information or services you must provide before installation. |
| Design and interfaces | Who is responsible where the court, foundations, drainage and electrical work meet. |
| Delivery and completion | Lead-time assumptions, installation window and handover conditions. |
| Warranty and maintenance | What is covered, by whom, and what maintenance the owner must carry out. |

Do not rank the totals until the missing work has been identified. Consider two hypothetical offers: one includes excavation and a designed base; the other assumes a suitable base already exists. The second number cannot be called cheaper for your project until the excluded work is assessed. This is a comparison principle, not a claim about actual contractor prices.

The next useful step is a site visit and two written offers using that common schedule. You are trying to buy a defined, usable result—not the lowest number beside the words “padel court”.

## FAQ

### Can I save money by using an existing tennis-court base?

Possibly, but reuse is a design question before it is a saving. Ask the designer and installer to confirm what they have inspected, what assumptions they are making and who accepts responsibility for the proposed solution. Do not deduct the entire groundworks allowance simply because a hard surface already exists.

### Does a sports club’s VAT exemption make the build VAT-free?

No automatic exemption should be assumed. HMRC distinguishes exempt sporting supplies from purchases made by the body, including construction of sports facilities. Ask a qualified adviser to confirm the project’s treatment and any recovery position before setting the cash budget.[^S07]

### What contingency percentage should I add?

This guide does not prescribe one. Start with the unresolved risks: ground conditions, design changes, utility work and quote exclusions. Ask the project adviser to explain the allowance against those risks. A generic percentage can disguise missing scope rather than deal with it.

[^S01]: LTA, [Padel Court Construction Guidance Note](https://www.lta.org.uk/siteassets/padel/lta-padel-court-construction-guidance-note-2025.pdf), 2025, “Size of Enclosure & Costs”, single-court column and footnotes; checked 8 September 2026.
[^S02]: International Padel Federation, [Rules of Padel](https://www.padelfip.com/wp-content/uploads/2025/12/FIP_Rules-of-Padel-1.pdf), application 1 January 2026, court specification.
[^S03]: Lofthouse Padel Court Specialists, [How much does a commercial padel court cost?](https://www.lofthousepadelcourtspecialists.co.uk/articles/how-much-does-a-commercial-padel-court-cost/), 19 January 2026; checked 8 September 2026.
[^S04]: S&C Slatter, [Padel Courts](https://www.slattersportsconstruction.com/padel-courts/), undated; checked 8 September 2026. Not used as a dated VAT-comparable quotation.
[^S05]: Wychavon District Council, [application W/26/01384/FUL](https://plan.wychavon.gov.uk/Planning/Display/W/26/01384/FUL), decision 7 September 2026; checked 8 September 2026.
[^S06]: UK government, [Determining a planning application](https://www.gov.uk/guidance/determining-a-planning-application), updated 8 April 2026; guidance for England.
[^S07]: HMRC, [Sport supplies that are VAT exempt (VAT Notice 701/45)](https://www.gov.uk/guidance/sport-supplies-that-are-vat-exempt-notice-70145), checked 8 September 2026.