What Does It Cost to Build a Padel Court in the UK?
A useful starting point is the LTA’s 2025 benchmark of £71,000 for one outdoor padel court, excluding VAT and fees. It separates £36,000 for the court with lights from £35,000 for the ring beam, base, ducting and drainage. It is a historical planning reference—not a guaranteed 2026 quotation, a national average or an all-inclusive budget for your site.S01
To find out what your court will cost, you need a site-specific offer covering both the playing enclosure and the work required to install it. A cheaper advertised court package can be a much smaller purchase, not a cheaper version of the same finished project.
This guide concerns one uncovered outdoor court in the UK, priced in GBP. Indoor buildings, canopies, land acquisition and operating a club are separate budget questions.
A useful benchmark, with its limits attached
Why not offer a broad current market range? Public contractor pages are not consistently comparable. Lofthouse’s article dated 19 January 2026 discusses different commercial packages but does not state a VAT basis. S&C Slatter’s public cost discussion does not establish a dated, VAT-explicit quotation suitable for a like-for-like comparison. Their headline numbers therefore cannot be combined into a defensible all-in 2026 range.S03S04
The practical answer is to keep the LTA figure attached to its year and exclusions, then replace each relevant allowance with an actual quotation for your site.
What an installed outdoor court quote must include
Use the following as a request-for-quotation schedule. It is a checklist of questions, not a claim that every item is included in the LTA benchmark or in every contractor’s package.
Give every bidder the same drawing and intended use. Our court-dimensions guide helps you describe the playing specification, while court basics explains the main parts of the enclosure. Neither replaces the designer’s assessment of the whole site.
Avoid specifying only a desirable label such as “panoramic.” Ask which exact system is being offered and what documents support its suitability for the proposed location. Price comparisons become useful only after the underlying specification is clear.
Costs outside the playing enclosure
Planning is particularly easy to mistake for a minor administrative extra. The technical rules of a sport do not grant local permission. FIP documentation describes the playing environment; the local planning authority considers a development in its own context.S02S06 Our FIP rules guide is a technical reference, not a planning approval.
A concrete English example shows why the distinction matters. On 7 September 2026, Wychavon District Council refused application W/26/01384/FUL for two padel courts with lighting. Its reasons included the absence of a noise and vibration impact assessment needed to consider the effect on nearby residents.S05
That does not mean every UK court requires the same report or will receive the same decision. It means your budget should identify what your authority needs before you assume the construction package is the whole project. Ask about noise, lighting, operating hours and the evidence required for this location. The cited national planning guidance applies to England; check the relevant national and local process elsewhere in the UK.S06
Keep VAT visible from the beginning. Request the net price, VAT treatment and amount payable rather than assuming an advertised figure is inclusive. Whether your organisation can recover any VAT is a separate, project-specific question for your adviser—not a discount to presume when comparing tenders.S07
Why a canopy or indoor court needs a different estimate
Ask a canopy supplier to define its structure, foundations, drainage, erection, connections with the court and the weather protection actually provided. Ask the court supplier which parts of its original design would change. Without that coordination, two apparently complete offers may leave responsibility for the connection between them unresolved.
For a court inside an existing building, investigate the building as well as the court package. Ask the relevant professionals about clear space, the existing floor, access, lighting, ventilation and the permissions or adaptations associated with the proposed use. These are questions to resolve, not a claim that the same alterations are necessary in every building.
A new indoor hall is a different project again. Do not compare its total with an outdoor structure-only price and label the difference “the cost of a roof.”
Our indoor-versus-outdoor guide explains the playing and equipment context. For a construction decision, insist on a separate scope and quotation for each scenario. No canopy or indoor price is included in the £71,000 benchmark above.
How to request and compare like-for-like quotes
A useful comparison sheet puts the scope before the total:
The next useful step is a site visit and two written offers using that common schedule. You are trying to buy a defined, usable result—not the lowest number beside the words “padel court”.
FAQ
Sources
[S01] LTA, Padel Court Construction Guidance Note, 2025, “Size of Enclosure & Costs”, single-court column and footnotes; checked 8 September 2026.
[S02] International Padel Federation, Rules of Padel, application 1 January 2026, court specification.
[S03] Lofthouse Padel Court Specialists, How much does a commercial padel court cost?, 19 January 2026; checked 8 September 2026.
[S04] S&C Slatter, Padel Courts, undated; checked 8 September 2026. Not used as a dated VAT-comparable quotation.
[S05] Wychavon District Council, application W/26/01384/FUL, decision 7 September 2026; checked 8 September 2026.
[S06] UK government, Determining a planning application, updated 8 April 2026; guidance for England.
[S07] HMRC, Sport supplies that are VAT exempt (VAT Notice 701/45), checked 8 September 2026.